Agricultural power distribution project in mountainous areas of Ethiopia

Business partner:Mountain Agricultural Development Plc
Project location: Ethiopia, Africa
Project date: September 17, 2023
Project description: Mountain Agricultural Development Co., Ltd. needed to replace farm power equipment, and contacted us for the first time in July 2023, and our company provided solutions according to the actual situation. The cooperation process is very happy, before delivery, the customer sent people to the factory for on-site inspection of goods, factory inspection, after confirming the correct delivery. In the installation process, our company also provided technical support, the equipment has been put into operation for more than half a year, the customer is very satisfied.
PROJECT EQUIPMENT | ||
Product name |
Specification and model |
quantity |
transformer |
S11-M-200KVA33/0.4KV |
1set |
transformer |
S11-M-315KVA33/0.4KV |
1set |
Low voltage cable entry cabinet |
GGD |
1set |
Box-type substation |
YB1250KVA |
1set |
Dual power cabinet |
ATS-2500 |
1set |
Vacuum circuit breaker |
ZW32-12FG/630 |
1set |